A snagging checklist records incomplete work and visible issues before handover. A handover pack organises the information the client needs to understand what has been delivered and how to look after it. Use these templates for a small interior project exercise and adapt them to the agreed scope.
A visual checklist does not certify electrical, structural, fire or other specialist work. Required inspections, tests and approvals must be completed by the appropriate competent people.
Agree what completion means before inspection
Collect the approved scope, current drawings, material references, samples and agreed changes. Identify which areas and items are included. Agree who attends the review and who can approve the resolution of an issue.
Judge the work against the agreed requirements. If a preference was never specified, discuss it as a possible change rather than automatically labelling it a defect. Keep the distinction between incomplete work, defective work and a new request clear in the record.
Use this room-by-room review checklist
| Area | Review prompts | Record |
|---|---|---|
| Walls and ceilings | Compare visible finish, edges and colour with the approved scope and samples. | Acceptable / issue / not assessed |
| Joinery and furniture | Compare delivered items, alignment and normal access with the agreed requirements. | Acceptable / issue / not assessed |
| Floor finishes | Record visible damage, incomplete edges and unresolved transitions for review. | Acceptable / issue / not assessed |
| Doors and storage | Review normal operation where safe and appropriate; record access problems. | Acceptable / issue / not assessed |
| Specified fixtures | Check that the agreed items are present and specialist review records are available where required. | Acceptable / issue / not assessed |
| Cleaning and protection | Record remaining debris, labels, protective coverings and agreed cleanup tasks. | Acceptable / issue / not assessed |
Do not operate an item that appears unsafe or dismantle work to investigate a concern. Record it and refer it to the responsible specialist. “Not assessed” is a useful status when an inspection falls outside your role.
Create a snag log with one issue per row
| Field | What to enter |
|---|---|
| Reference | A unique code, such as LR-01 for a living-room item. |
| Location | Room and precise position, linked to a photograph if useful. |
| Observation | Describe what is visible without guessing the cause. |
| Required review or action | State the agreed next step and approval needed. |
| Responsible person | Name or role responsible for responding. |
| Target date | An agreed date for action or review. |
| Status and evidence | Open, awaiting review or closed, with evidence and reviewer. |
A photograph helps locate an issue, but it may not establish its cause. Include a wider view and a closer view where practical, with permission. Keep the wording factual and avoid instructions that exceed your expertise.
Worked example: an incomplete finish
Reference: LR-01. Location: living-room wall beside the entrance. Observation: a visible unpainted patch remains at the edge of the agreed painted area. Next step: painting contractor to review against the approved scope and propose completion arrangements. Status: open until the work is reviewed and accepted by the nominated person.
This record is more useful than “painting bad.” It identifies the location, condition and responsibility without prescribing an unverified repair system.
Build a handover document index
Use a separate list for the approved scope and changes, final relevant drawings, installed product references, care instructions, supplier contacts, applicable warranties and specialist inspection or test records. Mark an item “not applicable” where appropriate instead of leaving an unexplained blank.
Record which documents have been received, who supplied them and where the current version is stored. Include any outstanding documents with a responsible person and agreed delivery date.
Close issues through review
Ask the responsible person to report completion, then arrange review by the appropriate person. Record the result and date. Do not close an item solely because someone says they attended the site.
At handover, summarise completed work, outstanding items and maintenance information clearly. Record the client’s questions and any agreed follow-up. Contractual acceptance and payment arrangements should follow the project’s actual agreement.
Practise the project-management process
Use this checklist alongside the fit-out planning guide. Ujenzi’s Interior Fit-Out and Project Management course develops a basic scope, budget, sequence and completion checklist. Enquire about the next class to confirm the learning arrangements.